Installing a TISS™(Treehouse Integrated Support System) strut assembly correctly is essential for maximizing the strength, stability, and lifespan of your treehouse support system.

Generally, you would not need to use struts or cables on anything smaller than a 6x12 TAB for a new build.
If you need more capacity, it is cheaper and simpler to just upgrade the connection (Lag Bolt to CORE TAB, CORE TAB to 3x9, then 3x9 to a 6x12), vs. adding a Strut or Suspension Cable. The support end of a TISS™ Kit uses up a couple of inches of Perch real estate, so it is better to use it on a 12" perch, to start with. We have installed struts on 3x9 TABs, but only very specific/unique applications.
If you require guidance on whether or not to add a TISS™ Kit to your build, please contact us.
This guide walks through the recommended installation procedure for Treehouse Supplies SD and HD strut systems. Whether you are building a new structure or reinforcing an existing platform, these steps will help ensure a safe and professional installation.
Tools & Materials Needed
Before beginning installation, gather the following tools and materials:
- 1-1/8” auger bit
- 1-5/8” auger bit (recommended for hardwoods)
- Drill with sufficient torque
- Water level
- Rubber mallet
- Sledgehammer with wood blocking
- Socket set and wrenches
- Included stainless steel spring clips
- TISS strut assemblies and hardware
Step 1: Mark the Through-Bar Installation Points
Determine the correct installation height based on:
- Platform height
- Beam depth
- Joist depth
- Decking thickness
Mark the desired installation point on one side of the tree. Then use a water level to transfer the exact height to the opposite side of the tree.
Accurate alignment is critical for proper load distribution.
Step 2: Drill the Through-Bar Hole
Using a 1-1/8” auger bit, drill approximately halfway through the tree from one side while keeping the bit as level as possible.
Next:
- Move to the opposite side of the tree.
- Drill toward the original hole until the two holes meet.
- Continue drilling from both sides until you have a continuous passage through the tree.
Pro Tip
Drilling from both sides typically produces straighter and more accurate results than attempting to drill completely through from one side only.
You may slightly widen the hole entrance by moving the auger bit around near the opening. This helps the through-bar slide into place more easily.
Step 3: Install the Through-Bar
Insert the through-bar into the drilled hole.
If necessary:
- Use a rubber mallet, or
- Place a wood block against the bar and tap it with a sledgehammer
This prevents damage to the powder-coated finish during installation.
Ensure the through-bar protrudes evenly from both sides of the tree before proceeding.
Step 4: Attach the Upper Strut Connections
Attach the upper strut connection brackets to each end of the through-bar using the included stainless steel spring clips.
Next:
- Thread the silver fork ends fully into the strut body
- Attach the strut assembly to the upper connection ear tabs
The hardware stack-up should follow this exact order:
Fork End → Washer → Ear Tab → Ear Tab → Washer → Fork End
The washers should sit between the fork ends and the ear tabs — not outside the fork assembly.
Install the nuts finger-tight only at this stage.

Step 5: Position the Lower Connection
Allow the strut assembly to hang straight downward from the upper connection. Then:
- Hold the lower connection at a right angle to the strut body, creating an “L” shape
- Rotate the assembly toward the tree until the lower connection contacts the bark
This establishes the drilling angle for the lower connection point.

Step 6: Drill the Lower Connection Hole
Insert the 1-1/8” auger bit into the tube portion of the lower connection and use the tube itself as a drilling guide.
Drill into the tree at a slight upward angle of approximately 15–20 degrees.
Once the hole has been started:
- Swing the strut assembly out of the way
- Continue drilling approximately 6” into the tree while maintaining the original upward angle
Step 7: Prepare the Lower Connection Seat
The tube section of the lower connection should be fully embedded into the tree.
To achieve this:
- Slightly widen the entrance hole by gently moving the auger bit around the opening, OR
- Use a 1-5/8” auger bit to enlarge the first 1-1/2” to 2” of the hole
This step is especially important in hardwood species where excessive resistance could damage the lag bolt threads.


Step 8: Tighten the Strut Hardware
Once the lower connection is fully seated:
- Tighten the nylock nuts on the upper and lower bolts
- Tighten only until there is no movement in the washers between the forks and ear tabs
Important
Do NOT over-tighten the assembly. The ear tabs should not be compressed inward toward each other.
Step 9: Pre-Load the Strut Assembly
The final step is to pre-load the strut system.
To do this:
- Grasp the strut barrel
- Rotate it until the assembly begins applying upward pressure to the through-bar above
- Continue until all slack is removed from the system
Once properly tensioned:
- Tighten the jam nuts at both ends of the strut body to lock the assembly in place
Important Threading Note
One jam nut uses right-hand threading (“righty-tighty”), while the opposite end uses left-hand threading (“lefty-tighty”).

Installation Tips & Best Practices
Protect Powder-Coated Hardware
Treehouse Supplies TABs and hardware are powder coated for corrosion resistance. Avoid using large pipe wrenches directly on the coating, as this can damage the finish.
Use the Correct Auger Sizes
Recommended auger sizes:
- 1-1/2” auger for softwoods
- 1-5/8” auger for hardwoods
Using the proper pilot hole size reduces installation stress and helps protect both the hardware and the tree.
Drill Collar Holes First
When installing large TAB systems, Treehouse Supplies recommends drilling the collar hole first before drilling the spindle hole.
This ensures proper centering and alignment during installation.
Final Thoughts